QCLNG Train 2: Acoustic Enclosure Refit
Australia Pacific LNG · Curtis Island
Issued 6 May 2026 · closes 13 Jun 2026 · valid 120 days · Dylan Fraser
Won but on hold, the turnaround window has moved twice.
Price, ex GST
$1,156,242
Cost build-up
$913,233
Margin
$243,009 21%
Markup applied
28%
on the cost build-up
QClad
Roofing · Cladding · Acoustics
Estimate
Q32113
Valid 120 days from 6 May 2026
To
Australia Pacific LNG
Sandeep Rao, Turnaround Engineer
sandeep.rao@aplng.com.au
ABN 68 001 646 331
Job
QCLNG Train 2: Acoustic Enclosure Refit
Curtis Island
Sector: Energy
Estimate closes 13 Jun 2026
Scope of works
Strip and replace the acoustic enclosure to the Train 2 compressor, with new absorption panel, barrier mat and isophonic mounts, and a verification test to the acoustic report.
Schedule of rates
| Item | Qty | Rate, ex GST | Amount |
|---|---|---|---|
| Preliminaries | |||
| RS-PRE-MOB Mobilisation & site establishment | 1 item | $18,450.00 | $18,450.00 |
| RS-PRE-SWM SWMS, JSA & site-specific safety plan | 1 item | $2,680.00 | $2,680.00 |
| RS-PRE-IND Site induction & verification of competency | 12 ea | $585.00 | $7,020.00 |
| RS-PRE-DEM Demobilisation & make good | 1 item | $7,420.00 | $7,420.00 |
| Acoustics | |||
| RS-ACO-ENC Plant acoustic enclosure, fabricate and install | 620 m² | $482.00 | $298,840.00 |
| RS-ACO-PNL Acoustic absorption panel, install | 1,480 m² | $229.00 | $338,920.00 |
| RS-ACO-BAR Mass-loaded acoustic barrier mat, install | 1,480 m² | $156.00 | $230,880.00 |
| RS-ACO-ISO Isophonic bracket & resilient mount system | 1,480 m² | $89.40 | $132,312.00 |
| RS-ACO-TST Post-installation acoustic verification test | 1 item | $4,280.00 | $4,280.00 |
| Height access | |||
| RS-HGT-ROP Rope access technician, IRATA | 78 day | $1,480.00 | $115,440.00 |
| Total, ex GST | $1,156,242.00 |
| GST at 10% | $115,624.20 |
| Total, inc GST | $1,271,866.20 |
Exclusions
- · Scaffold
- · Mechanical isolation
- · Marine transport
This tender is valid for 120 days from 6 May 2026 and is subject to QClad's standard conditions of subcontract. Quantities are measured from the tender documents and re-measured on completion. Payment terms 45 days EOM, retention 5%. All personnel hold current White Card, working-at-heights and site-specific inductions.
Dylan Fraser, Estimating Manager · QClad Services Pty Ltd · ABN 62 138 704 915 · QBCC 1174 320