Q32113 Demo QCLNG Train 2: Acoustic Enclosure Refit
Accounting connected Thu 13 Aug 2026
Q32113 Won Energy QJ2050

QCLNG Train 2: Acoustic Enclosure Refit

Australia Pacific LNG · Curtis Island

Issued 6 May 2026 · closes 13 Jun 2026 · valid 120 days · Dylan Fraser

Won but on hold, the turnaround window has moved twice.

Price, ex GST

$1,156,242

Cost build-up

$913,233

Margin

$243,009 21%

Markup applied

28%

on the cost build-up

QClad

Roofing · Cladding · Acoustics

Estimate

Q32113

Valid 120 days from 6 May 2026

To

Australia Pacific LNG

Sandeep Rao, Turnaround Engineer

sandeep.rao@aplng.com.au

ABN 68 001 646 331

Job

QCLNG Train 2: Acoustic Enclosure Refit

Curtis Island

Sector: Energy

Estimate closes 13 Jun 2026

Scope of works

Strip and replace the acoustic enclosure to the Train 2 compressor, with new absorption panel, barrier mat and isophonic mounts, and a verification test to the acoustic report.

Schedule of rates

ItemQtyRate, ex GSTAmount
Preliminaries
RS-PRE-MOB Mobilisation & site establishment 1 item $18,450.00 $18,450.00
RS-PRE-SWM SWMS, JSA & site-specific safety plan 1 item $2,680.00 $2,680.00
RS-PRE-IND Site induction & verification of competency 12 ea $585.00 $7,020.00
RS-PRE-DEM Demobilisation & make good 1 item $7,420.00 $7,420.00
Acoustics
RS-ACO-ENC Plant acoustic enclosure, fabricate and install 620 m² $482.00 $298,840.00
RS-ACO-PNL Acoustic absorption panel, install 1,480 m² $229.00 $338,920.00
RS-ACO-BAR Mass-loaded acoustic barrier mat, install 1,480 m² $156.00 $230,880.00
RS-ACO-ISO Isophonic bracket & resilient mount system 1,480 m² $89.40 $132,312.00
RS-ACO-TST Post-installation acoustic verification test 1 item $4,280.00 $4,280.00
Height access
RS-HGT-ROP Rope access technician, IRATA 78 day $1,480.00 $115,440.00
Total, ex GST$1,156,242.00
GST at 10%$115,624.20
Total, inc GST$1,271,866.20

Exclusions

  • · Scaffold
  • · Mechanical isolation
  • · Marine transport

This tender is valid for 120 days from 6 May 2026 and is subject to QClad's standard conditions of subcontract. Quantities are measured from the tender documents and re-measured on completion. Payment terms 45 days EOM, retention 5%. All personnel hold current White Card, working-at-heights and site-specific inductions.

Dylan Fraser, Estimating Manager · QClad Services Pty Ltd · ABN 62 138 704 915 · QBCC 1174 320