PC-2026-0191 Demo Mt Thorley Warkworth Mine Workshop: Roofing & Cladding · Jul 2026
Accounting connected Wed 5 Aug 2026
PC-2026-0191 Submitted Claim 12 · Jul 2026 PRJ-2025-036

Payment claim 12

Mt Thorley Warkworth Mine Workshop: Roofing & Cladding · Yancoal Australia

Final claim, including release of the first half of retention on practical completion.

Served

31 Jul 2026

Payment schedule due

21 Aug 2026

15 business days

Certified

-

Payment due

4 Sep 2026

25 business days

QClad

Roofing · Cladding · Acoustics

Payment claim

PC-2026-0191

Made under the Building Industry Fairness
(Security of Payment) Act 2017 (Qld)

Claimant

QClad Services Pty Ltd

ABN 62 138 704 915

QBCC 1174 320

Unit 2/9-11 Lenco Cres, Landsborough QLD 4550

07 5474 4966 · admin@qclad.com

Respondent

Yancoal Australia

ABN 82 111 859 119

Dean Copeland, Maintenance Superintendent

dean.copeland@yancoal.com.au

Warkworth NSW

Contract

YAN-MTW-WS-2025-6614

Mt Thorley Warkworth Mine Workshop: Roofing & Cladding

Mt Thorley Warkworth, Singleton, NSW

Reference date: 31 Jul 2026

Period: Jul 2026

Claim number: 12

Construction work carried out

Item Rate Measured Value, ex GST
RS-PRE-MOB Mobilisation & site establishment $18,450.00/item 1 item $18,450.00
RS-PRE-SWM SWMS, JSA & site-specific safety plan $2,680.00/item 1 item $2,680.00
RS-PRE-IND Site induction & verification of competency $585.00/ea 20 ea $11,700.00
RS-PRE-SUP Site supervision, leading hand $1,248.00/day 186 day $232,128.00
RS-LAB-TRV Travel & living away: per person, per day $385.00/day 880 day $338,800.00
RS-ROF-STR Strip existing roof sheeting & dispose $52.40/m² 3,860 m² $202,264.00
RS-ROF-KL7 KLIP-LOK 700 HI-STRENGTH roof sheeting, install $128.50/m² 3,860 m² $496,010.00
RS-ROF-INS Roof insulation blanket 75mm R1.8, install $39.60/m² 3,860 m² $152,856.00
RS-ROF-SAF Safety mesh, install to purlins $24.80/m² 3,860 m² $95,728.00
RS-CLD-CUS CUSTOM ORB wall cladding, install $102.40/m² 2,940 m² $301,056.00
RS-CLD-PUR Purlin & girt, supply and install $7,620.00/t 26.4 t $201,168.00
RS-ROF-GUT Box gutter, supply and install $385.00/lm 340 lm $130,900.00
RS-ROF-RDG Ridge capping & barge, supply and install $146.00/lm 420 lm $61,320.00
RS-ROF-DWP Downpipe & rainhead, supply and install $864.00/ea 38 ea $32,832.00
RS-HGT-ANC Roof anchor point: supply, install & certify $745.00/ea 52 ea $38,740.00
RS-HGT-STA Static line system: supply, install & certify $286.00/lm 520 lm $148,720.00
RS-WPF-SEA Sealant to laps, penetrations & flashings $34.80/lm 3,180 lm $110,664.00
RS-PRE-DEM Demobilisation & make good $7,420.00/item 1 item $7,420.00
RS-CLD-PUR Purlin & girt, supply and install · VAR-036-01 Purlin renewal, northern bays $7,620.00/t 6.2 t $47,244.00
RS-LAB-TRV Travel & living away: per person, per day · VAR-036-02 Wet weather standby, February $385.00/day 84 day $32,340.00
RS-PRE-SUP Site supervision, leading hand · VAR-036-02 Wet weather standby, February $1,248.00/day 14 day $17,472.00
RS-HGT-ANC Roof anchor point: supply, install & certify · VAR-036-03 Additional roof anchors to the crane runway $745.00/ea 22 ea $16,390.00
RS-HGT-STA Static line system: supply, install & certify · VAR-036-03 Additional roof anchors to the crane runway $286.00/lm 96 lm $27,456.00
Value of work in place to date$2,724,338.00
Less previously claimed (claims 1-11)($2,637,159.18)
Value of work this claim, ex GST$87,178.82
Less retention at 5%($4,358.94)
Net, ex GST$82,819.88
GST at 10%$8,281.99
Amount claimed, inc GST$91,101.87

This is a payment claim made under the Building Industry Fairness (Security of Payment) Act 2017 (Qld). The respondent must respond by giving a payment schedule within 15 business days of service, and must pay the scheduled amount on or before 4 Sep 2026. Retention of $4,358.94 is withheld under the contract, of which half is released at practical completion and the balance at the end of the defects liability period.

Prepared by Janelle Roe, Contracts Administrator · QClad Services Pty Ltd · ABN 62 138 704 915

Payment by EFT: NAB Caloundra · BSB 084-462 · Account 5813 02947 · Reference PC-2026-0191

Claim history on PRJ-2025-036

Cumulative to date: $2,724,338.00 of a $2,724,338 contract sum.

ClaimPeriodThis claimLodgedCertifiedPaidStatus
PC-2026-0177 Jun 2026 $179,806.30 30 Jun 2026 16 Jul 2026 1 Aug 2026 Paid