This is what Yancoal Australia see. Progress, claims, variations and issued documents. No rate build-up, no cost, no hours, no margin, and nothing about any other client.
Back to QClad's viewMt Thorley Warkworth Mine Workshop: Roofing & Cladding
Mt Thorley Warkworth, Singleton, NSW · your contract YAN-MTW-WS-2025-6614
19 Aug 2025 to 4 Jul 2026 · QClad contact Marcus Deng, 0411 748 902
Your subcontractor
QClad Services Pty Ltd
ABN 62 138 704 915 · QBCC 1174 320
Contract sum
$2,724,338
original $2,583,436 plus 3 approved variations
Work in place
$2,724,338
100% of the contract
Certified to date
$179,806
1 claim certified
Retention held
$4,495
5%, half released at PC
Progress by area
Measured on site, not estimated. This is the same measure the claim is built from.
$289,850 of $289,850
$1,171,910 of $1,171,910
$549,468 of $549,468
$231,306 of $231,306
$110,664 of $110,664
$371,140 of $371,140
Progress claims
Lodged under the Building Industry Fairness (Security of Payment) Act: 15 business days to a payment schedule, 25 to payment.
| Claim | Period | Lodged | Claimed, ex GST | Certified | Schedule due | Payment due | Status |
|---|---|---|---|---|---|---|---|
| PC-2026-0191 | 2026-07 | 8 Aug 2026 | $87,179 | - | 28 Aug 2026 | 11 Sep 2026 | Submitted |
| PC-2026-0177 | 2026-06 | 8 Jul 2026 | $179,806 | $179,806 | 29 Jul 2026 | 12 Aug 2026 | Paid |
PC-2026-0191, lodged 8 Aug 2026. A payment schedule has not been received. Under s.76 of the Act, a respondent who does not issue one inside the statutory period becomes liable for the full claimed amount.
Variations
3 approved and in the contract sum above. 0 submitted and awaiting your determination.
| Variation | What and why | Your reference | Raised | Value, ex GST | Status |
|---|---|---|---|---|---|
| VAR-036-03 | Additional roof anchors to the crane runway Yancoal added anchors along the runway for future maintenance access. | YAN-VO-3371 | 30 Apr 2026 | $43,846 | Approved 16 May 2026, Dean Copeland |
| VAR-036-02 | Wet weather standby, February Fourteen shifts lost to weather with crews in camp; standby claimed under the contract. | YAN-VO-3352 | 12 Mar 2026 | $49,812 | Approved 4 Apr 2026, Dean Copeland |
| VAR-036-01 | Purlin renewal, northern bays Corrosion beyond the allowance once the roof came off. | YAN-VO-3318 | 14 Nov 2025 | $47,244 | Approved 6 Dec 2025, Dean Copeland |
Documents issued to you
Current revision only. A superseded revision is never issued twice.
- Nothing issued yet.
Inspection and test plans
Hold points and witness points on your job, with what has been signed.
- Workshop roofing, Mt Thorley Warkworth ITP-036-01 5 of 5 signed