Mountain Creek SHS, Hall Re-roof
Mountain Creek State High School, Dept of Education · Mountain Creek
Issued 1 Apr 2026 · closes 2 May 2026 · valid 60 days · Priya Raghavan
Price, ex GST
$945,534
Cost build-up
$782,549
Margin
$162,985 17%
Markup applied
23%
on the cost build-up
QClad
Roofing · Cladding · Acoustics
Tender
T-2026-0118
Valid 60 days from 1 Apr 2026
To
Mountain Creek State High School, Dept of Education
Ian Bardsley, Facilities Officer
ian.bardsley@qed.qld.gov.au
ABN 76 337 613 647
Project
Mountain Creek SHS, Hall Re-roof
Mountain Creek
Sector: Commercial
Tender closes 2 May 2026
Scope of works
Strip and re-sheet the hall roof in KLIP-LOK 406 with insulation, safety mesh, new gutters and downpipes, plus edge protection for the duration.
Schedule of rates
| Item | Qty | Rate, ex GST | Amount |
|---|---|---|---|
| Preliminaries | |||
| RS-PRE-MOB Mobilisation & site establishment | 1 item | $18,450.00 | $18,450.00 |
| RS-PRE-SWM SWMS, JSA & site-specific safety plan | 1 item | $2,680.00 | $2,680.00 |
| RS-PRE-SUP Site supervision, leading hand | 68 day | $1,248.00 | $84,864.00 |
| RS-PRE-SCF Scaffold: supply, erect, hire 8 weeks, dismantle | 640 m² | $94.50 | $60,480.00 |
| RS-PRE-DEM Demobilisation & make good | 1 item | $7,420.00 | $7,420.00 |
| Roofing | |||
| RS-ROF-STR Strip existing roof sheeting & dispose | 1,980 m² | $52.40 | $103,752.00 |
| RS-ROF-KL4 KLIP-LOK 406 roof sheeting, install | 1,980 m² | $116.40 | $230,472.00 |
| RS-ROF-INS Roof insulation blanket 75mm R1.8, install | 1,980 m² | $39.60 | $78,408.00 |
| RS-ROF-SAF Safety mesh, install to purlins | 1,980 m² | $24.80 | $49,104.00 |
| RS-ROF-RDG Ridge capping & barge, supply and install | 224 lm | $146.00 | $32,704.00 |
| RS-ROF-GUT Box gutter, supply and install | 168 lm | $385.00 | $64,680.00 |
| RS-ROF-DWP Downpipe & rainhead, supply and install | 22 ea | $864.00 | $19,008.00 |
| Wall cladding | |||
| RS-CLD-CUS CUSTOM ORB wall cladding, install | 640 m² | $102.40 | $65,536.00 |
| Height access | |||
| RS-HGT-GRD Roof edge guardrail, install & hire | 386 lm | $124.00 | $47,864.00 |
| RS-HGT-ANC Roof anchor point: supply, install & certify | 24 ea | $745.00 | $17,880.00 |
| Weatherproofing | |||
| RS-WPF-SEA Sealant to laps, penetrations & flashings | 1,120 lm | $34.80 | $38,976.00 |
| RS-WPF-PEN Roof penetration flashing, form & seal | 34 ea | $684.00 | $23,256.00 |
| Total, ex GST | $945,534.00 |
| GST at 10% | $94,553.40 |
| Total, inc GST | $1,040,087.40 |
Exclusions
- · Asbestos removal
- · Ceiling works
- · Works during class hours
This tender is valid for 60 days from 1 Apr 2026 and is subject to QClad's standard conditions of subcontract. Quantities are measured from the tender documents and re-measured on completion. Payment terms 30 days, retention 5%. All personnel hold current White Card, working-at-heights and site-specific inductions.
Priya Raghavan, Estimator · QClad Services Pty Ltd · ABN 62 138 704 915 · QBCC 1174 320