QCLNG Train 2: Acoustic Enclosure Refit
Australia Pacific LNG · Curtis Island
Issued 28 Apr 2026 · closes 5 Jun 2026 · valid 120 days · Dylan Fraser
Won but on hold, the turnaround window has moved twice.
Price, ex GST
$1,156,242
Cost build-up
$913,233
Margin
$243,009 21%
Markup applied
28%
on the cost build-up
QClad
Roofing · Cladding · Acoustics
Tender
T-2026-0113
Valid 120 days from 28 Apr 2026
To
Australia Pacific LNG
Sandeep Rao, Turnaround Engineer
sandeep.rao@aplng.com.au
ABN 68 001 646 331
Project
QCLNG Train 2: Acoustic Enclosure Refit
Curtis Island
Sector: Energy
Tender closes 5 Jun 2026
Scope of works
Strip and replace the acoustic enclosure to the Train 2 compressor, with new absorption panel, barrier mat and isophonic mounts, and a verification test to the acoustic report.
Schedule of rates
| Item | Qty | Rate, ex GST | Amount |
|---|---|---|---|
| Preliminaries | |||
| RS-PRE-MOB Mobilisation & site establishment | 1 item | $18,450.00 | $18,450.00 |
| RS-PRE-SWM SWMS, JSA & site-specific safety plan | 1 item | $2,680.00 | $2,680.00 |
| RS-PRE-IND Site induction & verification of competency | 12 ea | $585.00 | $7,020.00 |
| RS-PRE-DEM Demobilisation & make good | 1 item | $7,420.00 | $7,420.00 |
| Acoustics | |||
| RS-ACO-ENC Plant acoustic enclosure, fabricate and install | 620 m² | $482.00 | $298,840.00 |
| RS-ACO-PNL Acoustic absorption panel, install | 1,480 m² | $229.00 | $338,920.00 |
| RS-ACO-BAR Mass-loaded acoustic barrier mat, install | 1,480 m² | $156.00 | $230,880.00 |
| RS-ACO-ISO Isophonic bracket & resilient mount system | 1,480 m² | $89.40 | $132,312.00 |
| RS-ACO-TST Post-installation acoustic verification test | 1 item | $4,280.00 | $4,280.00 |
| Height access | |||
| RS-HGT-ROP Rope access technician, IRATA | 78 day | $1,480.00 | $115,440.00 |
| Total, ex GST | $1,156,242.00 |
| GST at 10% | $115,624.20 |
| Total, inc GST | $1,271,866.20 |
Exclusions
- · Scaffold
- · Mechanical isolation
- · Marine transport
This tender is valid for 120 days from 28 Apr 2026 and is subject to QClad's standard conditions of subcontract. Quantities are measured from the tender documents and re-measured on completion. Payment terms 45 days EOM, retention 5%. All personnel hold current White Card, working-at-heights and site-specific inductions.
Dylan Fraser, Estimating Manager · QClad Services Pty Ltd · ABN 62 138 704 915 · QBCC 1174 320