QCLNG Train 2: Acoustic Enclosure Refit
Australia Pacific LNG · Curtis Island, Gladstone, QLD · contract APL-T2-TA26-3390
Marcus Deng · 7 Sep 2026 → 20 Nov 2026
Held pending the turnaround date moving. Hot-work permits and gas test before every cut; one calibrated 4-head detector per crew. Barge access only.
The position
Every figure below is the sum of rows on this page.
Contract sum
$1,156,242
- Tendered
- $1,156,242
- Approved variations
- +$0
Work in place
$2,680
- Complete
- 0.2%
- Still to run
- $1,153,562
Claimed & certified
$0
- Certified
- $0
- Unclaimed WIP
- $2,680
- Retention held
- $0
Margin
$392 14.6%
- Cost of work in place
- $2,288
- Against the build-up
- $0
- Committed, not received
- $0
Schedule of rates
Contract quantity, measured to date, and what each line is worth. Lines added by a variation carry its number.
| Rate | Rate, ex GST | Qty | Measured | Contract value | In place | Cost of it | Margin |
|---|---|---|---|---|---|---|---|
| Preliminaries | |||||||
| RS-PRE-MOB Mobilisation & site establishment | $18,450.00/item | 1 | 0 0% | $18,450 | $0 | $0 | - |
| RS-PRE-SWM SWMS, JSA & site-specific safety plan | $2,680.00/item | 1 | 1 100% | $2,680 | $2,680 | $2,288 | 15% |
| RS-PRE-IND Site induction & verification of competency | $585.00/ea | 12 | 0 0% | $7,020 | $0 | $0 | - |
| RS-PRE-DEM Demobilisation & make good | $7,420.00/item | 1 | 0 0% | $7,420 | $0 | $0 | - |
| Acoustics | |||||||
| RS-ACO-ENC Plant acoustic enclosure, fabricate and install | $482.00/m² | 620 | 0 0% | $298,840 | $0 | $0 | - |
| RS-ACO-PNL Acoustic absorption panel, install | $229.00/m² | 1,480 | 0 0% | $338,920 | $0 | $0 | - |
| RS-ACO-BAR Mass-loaded acoustic barrier mat, install | $156.00/m² | 1,480 | 0 0% | $230,880 | $0 | $0 | - |
| RS-ACO-ISO Isophonic bracket & resilient mount system | $89.40/m² | 1,480 | 0 0% | $132,312 | $0 | $0 | - |
| RS-ACO-TST Post-installation acoustic verification test | $4,280.00/item | 1 | 0 0% | $4,280 | $0 | $0 | - |
| Height access | |||||||
| RS-HGT-ROP Rope access technician, IRATA | $1,480.00/day | 78 | 0 0% | $115,440 | $0 | $0 | - |
| Total | $1,156,242 | $2,680 | $2,288 | 15% | |||
Variations
An approved variation's lines join the schedule of rates above on approval.
| No. | Variation | Raised | Their ref | Value, ex GST | Built | Status |
|---|---|---|---|---|---|---|
| No variations on this contract. | ||||||
Progress claims
Lodged under the QLD BIF Act: 15 business days to a payment schedule, 25 to payment. Retention at 5%.
| Claim | Period | This claim, ex GST | Retention | Inc GST | Lodged | Invoice | Status |
|---|---|---|---|---|---|---|---|
| Nothing claimed on this contract yet. | |||||||
Labour booked this week
0 hours, $0.00 of cost, off the crew app. 42 hours on this job to date.
| Day card | Person | Date | Task | Rate | Hours | Cost | Status |
|---|---|---|---|---|---|---|---|
| No hours booked to this job this week. | |||||||
Purchase orders
$0.00 committed and not yet received.
| PO | Supplier | Deliver to | Raised | Expected | Ex GST | Status |
|---|---|---|---|---|---|---|
| Nothing ordered against this job. | ||||||
Nothing recorded against this job yet.