PRJ-2026-050 Demo QCLNG Train 2: Acoustic Enclosure Refit
Accounting connected Wed 5 Aug 2026
PRJ-2026-050 On hold Energy

QCLNG Train 2: Acoustic Enclosure Refit

Australia Pacific LNG · Curtis Island, Gladstone, QLD · contract APL-T2-TA26-3390

Marcus Deng · 7 Sep 2026 → 20 Nov 2026

Held pending the turnaround date moving. Hot-work permits and gas test before every cut; one calibrated 4-head detector per crew. Barge access only.

The position

Every figure below is the sum of rows on this page.

Contract sum

$1,156,242

Tendered
$1,156,242
Approved variations
+$0

Work in place

$2,680

Complete
0.2%
Still to run
$1,153,562

Claimed & certified

$0

Certified
$0
Unclaimed WIP
$2,680
Retention held
$0

Margin

$392 14.6%

Cost of work in place
$2,288
Against the build-up
$0
Committed, not received
$0

Schedule of rates

Contract quantity, measured to date, and what each line is worth. Lines added by a variation carry its number.

Pricing schedule →
Rate Rate, ex GST Qty Measured Contract value In place Cost of it Margin
Preliminaries
RS-PRE-MOB Mobilisation & site establishment $18,450.00/item 1 0 0% $18,450 $0 $0 -
RS-PRE-SWM SWMS, JSA & site-specific safety plan $2,680.00/item 1 1 100% $2,680 $2,680 $2,288 15%
RS-PRE-IND Site induction & verification of competency $585.00/ea 12 0 0% $7,020 $0 $0 -
RS-PRE-DEM Demobilisation & make good $7,420.00/item 1 0 0% $7,420 $0 $0 -
Acoustics
RS-ACO-ENC Plant acoustic enclosure, fabricate and install $482.00/m² 620 0 0% $298,840 $0 $0 -
RS-ACO-PNL Acoustic absorption panel, install $229.00/m² 1,480 0 0% $338,920 $0 $0 -
RS-ACO-BAR Mass-loaded acoustic barrier mat, install $156.00/m² 1,480 0 0% $230,880 $0 $0 -
RS-ACO-ISO Isophonic bracket & resilient mount system $89.40/m² 1,480 0 0% $132,312 $0 $0 -
RS-ACO-TST Post-installation acoustic verification test $4,280.00/item 1 0 0% $4,280 $0 $0 -
Height access
RS-HGT-ROP Rope access technician, IRATA $1,480.00/day 78 0 0% $115,440 $0 $0 -
Total $1,156,242 $2,680 $2,288 15%