T-2025-0092 Demo Saraji Workshop Upgrade: Cladding
Accounting connected Wed 5 Aug 2026
T-2025-0092 Won Mining & Resources PRJ-2026-044

Saraji Workshop Upgrade: Cladding

BHP Mitsubishi Alliance · Saraji Mine, Dysart

Issued 15 Dec 2025 · closes 6 Feb 2026 · valid 90 days · Dylan Fraser

Price, ex GST

$2,470,624

Cost build-up

$2,008,131

Margin

$462,493 19%

Markup applied

27%

on the cost build-up

QClad

Roofing · Cladding · Acoustics

Tender

T-2025-0092

Valid 90 days from 15 Dec 2025

To

BHP Mitsubishi Alliance

Warren Idle, Contracts Lead, Saraji

warren.idle@bhp.com

ABN 33 096 412 752

Project

Saraji Workshop Upgrade: Cladding

Saraji Mine, Dysart

Sector: Mining & Resources

Tender closes 6 Feb 2026

Scope of works

Strip and replace roof sheeting and wall cladding to the heavy workshop, purlin renewal, louvres, personnel doors and a certified anchor system.

Schedule of rates

ItemQtyRate, ex GSTAmount
Preliminaries
RS-PRE-MOB Mobilisation & site establishment 1 item $18,450.00 $18,450.00
RS-PRE-SWM SWMS, JSA & site-specific safety plan 1 item $2,680.00 $2,680.00
RS-PRE-IND Site induction & verification of competency 16 ea $585.00 $9,360.00
RS-PRE-SUP Site supervision, leading hand 126 day $1,248.00 $157,248.00
RS-PRE-DEM Demobilisation & make good 1 item $7,420.00 $7,420.00
Labour & plant
RS-LAB-TRV Travel & living away: per person, per day 640 day $385.00 $246,400.00
Wall cladding
RS-CLD-STR Strip existing wall cladding & dispose 3,180 m² $48.60 $154,548.00
RS-CLD-KL7 KLIP-LOK 700 wall cladding, install 3,180 m² $142.40 $452,832.00
RS-CLD-PUR Purlin & girt, supply and install 18.4 t $7,620.00 $140,208.00
RS-CLD-LOU Weatherproof louvre panel, install 168 m² $346.00 $58,128.00
RS-CLD-DOR Personnel access door in cladding, form and trim 6 ea $1,840.00 $11,040.00
RS-CLD-FLA Custom flashings, supply and install 1,240 lm $114.00 $141,360.00
Roofing
RS-ROF-STR Strip existing roof sheeting & dispose 2,640 m² $52.40 $138,336.00
RS-ROF-KL7 KLIP-LOK 700 HI-STRENGTH roof sheeting, install 2,640 m² $136.80 $361,152.00
RS-ROF-INS Roof insulation blanket 75mm R1.8, install 2,640 m² $39.60 $104,544.00
RS-ROF-SAF Safety mesh, install to purlins 2,640 m² $24.80 $65,472.00
RS-ROF-VNT Ridge ventilator, supply and install 96 lm $624.00 $59,904.00
RS-ROF-RDG Ridge capping & barge, supply and install 268 lm $146.00 $39,128.00
Height access
RS-HGT-SPI Spider lift hire & operator, 28m 84 day $2,360.00 $198,240.00
RS-HGT-ANC Roof anchor point: supply, install & certify 38 ea $745.00 $28,310.00
Weatherproofing
RS-WPF-SEA Sealant to laps, penetrations & flashings 2,180 lm $34.80 $75,864.00
Total, ex GST$2,470,624.00
GST at 10%$247,062.40
Total, inc GST$2,717,686.40

Exclusions

  • · Crane isolation
  • · Overhead services relocation
  • · Asbestos

This tender is valid for 90 days from 15 Dec 2025 and is subject to QClad's standard conditions of subcontract. Quantities are measured from the tender documents and re-measured on completion. Payment terms 45 days EOM, retention 5%. All personnel hold current White Card, working-at-heights and site-specific inductions.

Dylan Fraser, Estimating Manager · QClad Services Pty Ltd · ABN 62 138 704 915 · QBCC 1174 320