QClad
QClad
T-2025-0088 Demo Boyne Smelters Stockpile Shed: Re-clad & Acoustics
Accounting connected Wed 5 Aug 2026
T-2025-0088 Won Mining & Resources PRJ-2026-038

Boyne Smelters Stockpile Shed: Re-clad & Acoustics

Rio Tinto Aluminium · Boyne Island

Issued 6 Nov 2025 · closes 9 Jan 2026 · valid 90 days · Dylan Fraser

Price, ex GST

$2,542,100

Cost build-up

$2,165,756

Margin

$376,344 15%

Markup applied

26%

on the cost build-up

QClad

Roofing · Cladding · Acoustics

Tender

T-2025-0088

Valid 90 days from 6 Nov 2025

To

Rio Tinto Aluminium

Grant Hollows, Superintendent, Fixed Plant

grant.hollows@riotinto.com

ABN 15 009 679 127

Project

Boyne Smelters Stockpile Shed: Re-clad & Acoustics

Boyne Island

Sector: Mining & Resources

Tender closes 9 Jan 2026

Scope of works

Re-clad the stockpile shed and install an acoustic enclosure to the transfer tower, verified by independent sound test.

Schedule of rates

ItemQtyRate, ex GSTAmount
Preliminaries
RS-PRE-MOB Mobilisation & site establishment 1 item $18,450.00 $18,450.00
RS-PRE-SWM SWMS, JSA & site-specific safety plan 1 item $2,680.00 $2,680.00
RS-PRE-IND Site induction & verification of competency 14 ea $585.00 $8,190.00
RS-PRE-SUP Site supervision, leading hand 118 day $1,248.00 $147,264.00
RS-PRE-DEM Demobilisation & make good 1 item $7,420.00 $7,420.00
Wall cladding
RS-CLD-STR Strip existing wall cladding & dispose 4,260 m² $48.60 $207,036.00
RS-CLD-CUS CUSTOM ORB wall cladding, install 4,260 m² $107.80 $459,228.00
RS-CLD-FLA Custom flashings, supply and install 980 lm $114.00 $111,720.00
Roofing
RS-ROF-TRM TRIMDEK roof sheeting, install 1,880 m² $97.80 $183,864.00
Acoustics
RS-ACO-PNL Acoustic absorption panel, install 1,240 m² $229.00 $283,960.00
RS-ACO-LIN Perforated acoustic liner tray, install 860 m² $264.00 $227,040.00
RS-ACO-BAR Mass-loaded acoustic barrier mat, install 1,240 m² $156.00 $193,440.00
RS-ACO-ISO Isophonic bracket & resilient mount system 1,240 m² $89.40 $110,856.00
RS-ACO-ENC Plant acoustic enclosure, fabricate and install 380 m² $482.00 $183,160.00
RS-ACO-TST Post-installation acoustic verification test 1 item $4,280.00 $4,280.00
Height access
RS-HGT-ROP Rope access technician, IRATA 96 day $1,480.00 $142,080.00
RS-HGT-STA Static line system: supply, install & certify 320 lm $286.00 $91,520.00
Weatherproofing
RS-WPF-SEA Sealant to laps, penetrations & flashings 2,640 lm $34.80 $91,872.00
RS-WPF-MEM Liquid-applied weatherproof membrane 420 m² $162.00 $68,040.00
Total, ex GST$2,542,100.00
GST at 10%$254,210.00
Total, inc GST$2,796,310.00

Exclusions

  • · Conveyor stoppage outside the nominated windows
  • · Structural steel

This tender is valid for 90 days from 6 Nov 2025 and is subject to QClad's standard conditions of subcontract. Quantities are measured from the tender documents and re-measured on completion. Payment terms 45 days EOM, retention 5%. All personnel hold current White Card, working-at-heights and site-specific inductions.