QClad
QClad
PRJ-2024-009 Demo Rio Tinto Boyne Smelters: Potline Cladding
Accounting connected Wed 5 Aug 2026
PRJ-2024-009 Complete Mining & Resources

Rio Tinto Boyne Smelters: Potline Cladding

Rio Tinto Aluminium · Boyne Island, Gladstone, QLD · contract RTA-BSL-PL-2022-3318

Marcus Deng · 30 Jan 2023 → 24 Mar 2023 · PC 5 Apr 2023 · DLP ends 5 Apr 2024

The position

Every figure below is the sum of rows on this page.

Contract sum

$430,590

Tendered
$430,590
Approved variations
+$0

Work in place

$430,590

Complete
100.0%
Still to run
$0

Claimed & certified

$430,590

Certified
$430,590
Unclaimed WIP
$0
Retention held
$0

Margin

$78,299 18.2%

Cost of work in place
$352,291
Against the build-up
-$6,200
Committed, not received
$0

Schedule of rates

Contract quantity, measured to date, and what each line is worth. Lines added by a variation carry its number.

Pricing schedule →
Rate Rate, ex GST Qty Measured Contract value In place Cost of it Margin
Preliminaries
RS-PRE-MOB Mobilisation & site establishment $18,450.00/item 1 1 100% $18,450 $18,450 $15,224 17%
RS-PRE-SUP Site supervision, leading hand $1,248.00/day 42 42 100% $52,416 $52,416 $43,470 17%
RS-PRE-DEM Demobilisation & make good $7,420.00/item 1 1 100% $7,420 $7,420 $6,316 15%
Wall cladding
RS-CLD-STR Strip existing wall cladding & dispose $48.60/m² 1,480 1,480 100% $71,928 $71,928 $66,585 7%
RS-CLD-CUS CUSTOM ORB wall cladding, install $102.40/m² 1,480 1,480 100% $151,552 $151,552 $125,578 17%
Height access
RS-HGT-ROP Rope access technician, IRATA $1,480.00/day 64 64 100% $94,720 $94,720 $74,240 22%
Weatherproofing
RS-WPF-SEA Sealant to laps, penetrations & flashings $34.80/lm 980 980 100% $34,104 $34,104 $27,077 21%
Total $430,590 $430,590 $358,491 17%