Wacol Distribution Centre, Cladding & Roofing
Walz Group · Wacol
Issued 26 Jun 2026 · closes 14 Aug 2026 · valid 60 days · Priya Raghavan
Price, ex GST
$1,460,526
Cost build-up
$1,184,131
Margin
$276,395 19%
Markup applied
20%
on the cost build-up
QClad
Roofing · Cladding · Acoustics
Tender
T-2026-0125
Valid 60 days from 26 Jun 2026
To
Walz Group
Tim Kessell, Operations Manager
tim.kessell@walz.com.au
ABN 31 093 462 088
Project
Wacol Distribution Centre, Cladding & Roofing
Wacol
Sector: Industrial
Tender closes 14 Aug 2026
Scope of works
New KLIP-LOK 700 wall cladding and TRIMDEK roof sheeting to the distribution centre, flashings, personnel doors and sealant.
Schedule of rates
| Item | Qty | Rate, ex GST | Amount |
|---|---|---|---|
| Preliminaries | |||
| RS-PRE-MOB Mobilisation & site establishment | 1 item | $18,450.00 | $18,450.00 |
| RS-PRE-SUP Site supervision, leading hand | 64 day | $1,248.00 | $79,872.00 |
| RS-PRE-DEM Demobilisation & make good | 1 item | $7,420.00 | $7,420.00 |
| Wall cladding | |||
| RS-CLD-KL7 KLIP-LOK 700 wall cladding, install | 4,180 m² | $134.80 | $563,464.00 |
| RS-CLD-FLA Custom flashings, supply and install | 1,180 lm | $114.00 | $134,520.00 |
| RS-CLD-DOR Personnel access door in cladding, form and trim | 8 ea | $1,840.00 | $14,720.00 |
| Roofing | |||
| RS-ROF-TRM TRIMDEK roof sheeting, install | 3,240 m² | $97.80 | $316,872.00 |
| RS-ROF-INS Roof insulation blanket 75mm R1.8, install | 3,240 m² | $39.60 | $128,304.00 |
| Height access | |||
| RS-HGT-EWP EWP hire & operator, 45ft boom | 68 day | $1,780.00 | $121,040.00 |
| Weatherproofing | |||
| RS-WPF-SEA Sealant to laps, penetrations & flashings | 2,180 lm | $34.80 | $75,864.00 |
| Total, ex GST | $1,460,526.00 |
| GST at 10% | $146,052.60 |
| Total, inc GST | $1,606,578.60 |
Exclusions
- · Structural steel
- · Concrete works
- · Fire services penetrations
This tender is valid for 60 days from 26 Jun 2026 and is subject to QClad's standard conditions of subcontract. Quantities are measured from the tender documents and re-measured on completion. Payment terms 30 days, retention 5%. All personnel hold current White Card, working-at-heights and site-specific inductions.
Priya Raghavan, Estimator · QClad Services Pty Ltd · ABN 62 138 704 915 · QBCC 1174 320